March 18, 2018 court of first instance - Orders
Claim No: CFI-023-2017
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
MELOUD BENFETTA
and
DAMAC PARK TOWERS COMPANY LIMITED
ORDER OF H.E. JUSTICE OMAR AL MUHAIRI
UPON reviewing the Defendant’s Application No. CFI-023-2017/2 dated 15 January 2018 seeking to set aside the Default Judgment of Judicial Officer Nassir Al Nasser dated 25 September 2017 (the “Application”)
AND PURSUANT TO Part 14.1 and 14.2 of the Rules of the DIFC Courts
IT IS HEREBY ORDERED THAT:
1.The Application is granted.
2. The Default Judgment dated 25 September 2017 issued by Judicial Officer Nassir Al Nasser is set aside.
3. The Claimant file and serve its statement of case and particulars of claim within 14 days from the date of this Order.
4. The Defendant shall file and serve its defence to the statement of case and particulars of claim within 28 days after service of the particulars of claim.
Issued by:
Ayesha Bin Kalban
Assistant Registrar
Date of issue: 18 March 2018
At: 4pm