February 05, 2024 COURT OF FIRST INSTANCE - ORDERS
Claim No. CFI 034/2022
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
ICICI BANK LIMITED
Claimant
and
BAVAGUTHU RAGHURAM SHETTY
Defendant
CONSENT ORDER
UPON the Parties having agreed an updated procedural timetable
AND UPON reviewing the Rules of the DIFC Courts (the "RDC")
AND UPON reviewing the Case Management Order of H.E. Justice Nassir Al Nasser (the "CMO")
AND UPON reviewing the Consent Order dated 19 January 2024 (the "Consent Order")
IT IS HEREBY ORDERED BY CONSENT THAT:
1. The procedural timetable shall be amended as follows:
Production of Documents (RDC Part 28)
(1) Standard Production shall be made by each party by no later than 4pm on 9 February 2024.
(2) All other directions in the CMO and the Consent Order are unamended.
Issued by:
Hayley Norton
Assistant Registrar
Date of issue: 5 February 2024
At: 12pm