UPON the Claimant and Third Defendant having agreed the terms of the following order
IT IS ORDERED BY CONSENT BETWEEN THE CLAIMANT AND THE THIRD DEFENDANT THAT:
1. The Consent Order dated 29 April 2021 will have no effect.
2. The Case Management Order of H.E. Justice Ali Al Madhani issued on 28 February 2021 is amended as follows:
a. at paragraph 5 replace “29 April 2021” with “10 June 2021”;
b. at paragraph 6 replace “27 May 2021” with “8 July 2021”; and
c. at paragraph 7 replace “24 June 2021” with “19 August 2021”
3. No order as to costs.