April 27, 2021 court of first instance - Orders
Claim No. CFI 070/2018
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
IDBI BANK LIMITED
Claimant/Respondent
and
(1) MABANI DELMA GENERAL CONTRACTING CO LLC
(2) HELIOPOLIS ELECTRIC COMPANY LLC
(3) DELMA ENGINEERING PROJECTS COMPANY LLC
(4) DELMA EMIRATES DIESEL
(5) DELMA EMIRATES GENERAL TRANSPORT
(6) AHMED KHALIL KHALED ALMERAIKHI
(7) SHERIFA AHMED KHALIL KHALED ALMERAIKHI
(8) MARIAM AHMED KHALED ALMERAIKHI
Defendants/Applicants
CONSENT ORDER
UPON the agreement of the Claimant and the Defendants to the following case management directions and procedural timetable:
IT IS HEREBY ORDERED BY CONSENT THAT:
1. The date for the Defendants to file their Defence shall be determined once the Claimant’s application for discontinuance of the claim against the Second Defendant, Heliopolis Electric Company LLC dated 19 April 2021 (the “Discontinuance Application”) is determined.
2. The Defendants shall file their Defence(s) no later than 7 days after Claimant has filed the Particulars of Claim with the amendments resulting from the Discontinuance Application.
3. The parties will agree on the consequential revised amendments of the procedural timetable and the CMC Order after the Discontinuance Application is determined.
4. Costs in the case with respect to the amendments of the Particulars of Claim and the Defence.
Issued by:
Nour Hineidi
Registrar
Date of issue: 27 April 2021
At: 2.30pm