April 27, 2021 court of first instance - Orders
Claim No. CFI 097/2020
THE DUBAI INTERNATIONAL FINANCIAL CENTRE COURTS
IN THE COURT OF FIRST INSTANCE
BETWEEN
LAILA HABIB AHMAD SHUAIB
Claimant
and
DANUBE PROPERTIES DEVELOPMENT LLC
Defendant
ORDER OF H.E JUSTICE OMAR AL MUHAIRI
UPON reviewing the Defendant’s Application No. CFI-097-2020/1 dated 7 December 2020 contesting the jurisdiction of the DIFC Courts
AND UPON reviewing the Witness Statement of Peter Wood dated 7 December 2020 and exhibit
AND UPON reviewing the Second Witness Statement of Peter Wood dated 11 January 2021 and exhibit
AND UPON reviewing the Third Witness Statement of Peter Wood dated 2 February 2021 and exhibit
AND UPON reviewing the parties’ skeleton arguments
AND UPON reviewing the Defendant’s written submission on costs dated 13 April 2021
AND UPON reviewing the Claimant’s memorandum dated 19 April 2021
IT IS HERBY ORDERED THAT:
1. CFI-097-2020 be discontinued.
2. The Claimant shall pay the Defendant’s costs of the proceedings, in the total amount of AED 118,735.50, to be summarily assessed.
3. Liberty to apply.
Issued by:
Nour Hineidi
Registrar
Date of issue: 27 April 2021
At: 1.00pm